Humidification Plant Automation System
HUMIDIFICATION PLANT AUTOMATION
Control logics is the brain of the entire DDC Systems.
Control logics are programmed with SET software and are loaded in the Web Enabled Controller. The controller for Spinning Department has been programmed for the following sequence.
1.
The
system is powered ON.
2. The
System Checks for Auto/Manual Switch. If the switch is in Auto the controller
executes further program.
3. The
system checks for time program. By Programming the start and stop time in
advance the system start /stop the Humidification plant. The time schedules can
be programmed to take into the seasonal conditions, maintenance schedules etc.
4. The
System then checks for alarms present in the system like high/low humidity,
temperature alarms etc. The alarm are
recorded in alarm log and necessary action are taken to meet the requirement . In case
of no alarm it proceeds further.
5. Based on the department RH and Temperature the
controller perform the following sequence
1. If Department RH is less the required Setpoint the Controller Switches ‘ON’ the air washer pump and operates damper depending on department Temperature.
2. If
Department RH is more than the setpoint it switches ‘OFF’ the Air Washer Spray
Pump and depending on department RH and Temperature operates the dampers to
meet the required conditions inside the department.
Optional Items:
The Controller has the option of being programmed for display of Department Enthalpy, Moisture, Air washer Efficiency, dewpoint temperatures , Department CFM etc.
Introduction:
The Web Enabled controller uses Ethernet and TCP/IP technologies.
Each controller incorporates a web server which can deliver user specific Web pages to a PC or mobile running with a internet browser.
With a basic module of 16 I/O and expandable upto 192 I/O channels the controller can be programmed to suit any application.
As You are aware humidification plant room is designed for peak summer conditions and this conditions remains in a year for only few hours in a day and few days in a month.
So with varying outside air conditions the damper and air washer pump has to be dynamically operated in order to maintain the required department conditions.
The repeatability and accuracy in maintaining the department RH and temperature counts in maintaining the Quality of the Yarn.
So a manual operation of dampers and pump control is very difficult.
By using web enabled controller the RH can be controlled to a precision of +/-2%.
The controller is mounted inside a panel and erected near the MCC of respective Humidification Plant or inside the department.
The controller is connected to the field devices like Humidity & Temperature Sensor, Damper Actuator etc.
![]() |
| Damper Actuator |
The controller will be programmed to control the damper and air washer pump by sensing department RH and temperature.
![]() |
| Humidity & Temperature sensor |
The department temperature will be maintained at a optimum level.
The department RH and Temperature can be recorded i.e 1000 readings for analysis purpose.
Alarms will be continuously logged in the controller. The alarm acknowledged and not acknowledged can be viewed.
The department RH, temperature setpoints are field settable to offer flexibility in operation.
The Web Enabled controller uses Ethernet and TCP/IP technologies.
Each controller incorporates a web server which can deliver user specific Web pages to a PC running with a internet browser.
Using Trend 963 graphical animation software all the parameters we can see on the screen. With a basic module of 16 I/O and expandable upto 192 I/O channels.
The controller is mounted inside a panel and erected near the MCC of respective Humidification Plant or inside the department.
The controller is connected to the field devices like Humidity & temperature sensor, damper actuator, valve actuator, variable frequency drive etc.
The controller will be programmed to control the damper and air washer pump by sensing department RH and temperature.
The department temperature will be maintained at a optimum level. The department RH and Temperature can be recorded i.e 1000 readings for analysis purpose.
"Alarms" will be continuously logged in the controller.
The alarm acknowledged and not acknowledged can be viewed. The department RH, temperature setpoints are field settable to offer flexibility in operation.